Work on the Village Hall upgrade will start in Spring 2018
The Committee has been successful in raising funds for what we have previously call Phase1 and Phase2 of a 4 phase program to deliver the Hall that we have previously presented and is currently illustrated on the Ormside Village Hall – Revised Plan below.
To remind you:
Phase1- Main Hall
A total overhaul with:
Removal of existing wall coverings
Improved insulation
Redecoration
Improved Heating and the installation of Hot Water
Phase 2 – Kitchen and Lobby/Toilet Areas
A total overhaul with:
New Kitchen and cooking facilities
Creation of a welcoming Entrance Hall
Redecorated and improved Toilets
Phase 3 – New Supper Room /Hall Extension
Phase 4 – Access and Landscaping
can’t wait to see the transformation !